The 1.2-mile stretch of Division Street between Route 25 and Kirk Road, which runs along the border between Geneva and St. Charles, is set to be repaved next year.

On Nov. 16, both city councils approved an intergovernmental agreement, a contract between the two cities that spells out who manages the project and how they split the bill. According to Geneva city documents, the repaving will happen in summer 2027.

Here's what to know:

  • Project payment: City documents estimate that construction will cost about $1.09 million, plus about $109,000 for engineering. A $585,676 Surface Transportation Program grant, awarded in 2022 through the Kane-Kendall Council of Mayors, is expected to cover about 54% of construction. According to St. Charles city documents, the two cities split the rest evenly.

  • How the project came to be: According to a Geneva Public Works memo, the project dates back to 2020, when the city began planning water main replacements after service disruptions on East State Street, North Bennett Street, and Division Street. St. Charles also needs to replace a water main on the north side of Division Street before repaving can begin.

  • What drivers will see: A Geneva official said no detour is planned. Crews are expected to repave in sections, and plans also include patching, curb and sidewalk work, and adjusting or replacing some storm drains.

Officials discussed possible bike infrastructure upgrades to the corridor as well. St. Charles is acting as the lead agency on the project.